An eight-year-old judgment has no single answer, because the question depends on the state and on two clocks, not one. The lien that holds the land runs on its own term and can expire while the judgment behind it is still enforceable. This page names the filing that keeps a lien alive in the states whose statutes spell it out, and says plainly where the statute stops short. It is not legal advice, and it will not compute the date your own lien ends.

Listen instead

The same material, read aloud and told more loosely than it is written. Nothing is said in it that this page does not also say.

Lien life against judgment life

Two clocks run here, and they are not the same clock. The judgment's life is how long it can be enforced. The 's life is how long it holds land, and in several states the lien ends first.

Start with New York, because it shows the trap in miniature. A judgment's against transfers of the debtor's real property runs from the time of docketing in the county until ten years after the was filed. CPLR 52031 ties the end date to the judgment-roll, not to the county docketing. When a transcript of the docket is filed with the clerk of any other county, that clerk dockets the judgment too, under CPLR 50182. How long the New York judgment itself may be enforced is a separate period this page does not state.

The two clocks pull apart hardest where the lien is the shorter one. Colorado's lien expires six years after entry unless the judgment is , while execution may issue for twenty. C.R.S. 13-52-1023 carries both numbers in one section. Indiana and Iowa each give the lien ten years and the judgment twenty. IC 34-55-9-24 and IC 34-11-2-125 set Indiana's pair; Iowa Code 624.236 and Iowa Code 614.17 set Iowa's. Alabama runs the same split, a ten-year lien under Ala. Code 6-9-2118 and a judgment that cannot be revived after twenty under Ala. Code 6-9-1909.

Elsewhere the lien keeps time by the judgment's own pulse. In Michigan the lien expires five years after recording, and sooner if the judgment expires first. MCL 600.280910 says so in two subsections. The District of Columbia lien continues as long as the judgment is in force, and D.C. Code 15-10111 makes a filed money judgment enforceable by execution for twelve years. A Hawaii lien cannot outlast the judgment, which HRS 657-512 presumes paid and discharged ten years after a Hawaii state court renders it unless extended. West Virginia's lien lives as long as the judgment is valid and enforceable, under W. Va. Code 38-3-613.

And in a cluster of states the lien ends not on a fixed anniversary but when the judgment goes . Ohio is the clearest: the judgment stops operating as a lien unless an execution, a filed , a garnishment, or a proceeding in aid of execution occurs within five years. Ohio Rev. Code 2329.0714 lists them. Nebraska and Wyoming set a five-year dormancy of the same shape, under Neb. Rev. Stat. 25-151515 and Wyo. Stat. 1-17-30716. Georgia's judgment goes dormant and may not be enforced when seven years pass without an execution issued and entered on the , under O.C.G.A. 9-12-6017. Oklahoma's judgment becomes unenforceable after five years without a listed filing, under 12 O.S. 73518.

Two states sit outside the pattern, and the honest answer is to say so. New Mexico provides that a judgment may be enforced for not more than fourteen years, under NMSA 39-1-619, but the statute does not state a separate term for the lien on real estate, and this page states none. For New Jersey the statutes give no term for a judgment's hold on real estate, so none is stated here either. A longer treatment of how each state's lien attaches is in how a judgment becomes a lien across the states.

Several states drawn as paired windows in years, lien against judgment, from the date each statute counts from. New York's lien runs ten years from filing of the judgment-roll under CPLR 5203. Colorado's lien runs six years from entry under C.R.S. 13-52-102 while execution may issue for twenty. Indiana's lien runs ten years under IC 34-55-9-2 while the judgment is considered satisfied after twenty under IC 34-11-2-12. Iowa's lien runs ten years under Iowa Code 624.23 while actions on the judgment have twenty under Iowa Code 614.1. Alabama's lien runs ten years under Ala. Code 6-9-211 while the judgment cannot be revived after twenty under Ala. Code 6-9-190. Michigan's lien runs five years from recording under MCL 600.2809. Florida's real property lien runs ten years from recording under Fla. Stat. 55.10 but no lien survives twenty years from entry under Fla. Stat. 55.081.

Where the lien is the shorter clock, a judgment creditor who stops counting at the judgment's twenty years has already lost the land years earlier.

Renewal by any other name

The filing that keeps a lien alive goes by a different word in almost every state. Renewal, extension, revival, rerecording, an action on the judgment. Group them by what is filed and where, and the map gets smaller.

Some renewals happen in the . Florida extends its real property lien ten years by rerecording a before it expires, with an affidavit of the lienholder's current address, under Fla. Stat. 55.1020, and never past twenty years from entry under Fla. Stat. 55.08121. Michigan rerecords a second notice once, at least 120 days before expiry, good for five more years, under MCL 600.2809. Kentucky files a notice of renewal at least 120 days before expiry, once, for up to five years, under KRS 426.72022. Utah records a renewing document in each county where the lien is recorded, under Utah Code 78B-5-20223.

Some renewals happen in the court file instead. California files an application for renewal under Cal. Code Civ. Proc. 683.12024, and records a certified copy to carry the lien under Cal. Code Civ. Proc. 683.18025. Maryland files a notice of renewal under Md. Rule 2-62526; Mississippi files a Notice of Renewal of Judgment under Miss. Code 15-1-4327; Oregon files a certificate of extension under ORS 18.18228; Idaho moves for an order renewing judgment under Idaho Code 10-111129.

And some renewals are court proceedings that revive a judgment already gone dormant. The District of Columbia issues an order of revival under D.C. Code 15-10330. Illinois revives and records a new memorandum under 735 ILCS 5/12-10131. Kansas moves for revivor under K.S.A. 60-240432. Pennsylvania issues a writ of revival under Pa.R.C.P. 302533. Texas revives by scire facias or action of debt, not later than the second anniversary of dormancy, under Tex. Civ. Prac. & Rem. Code 31.006. Georgia renews or revives within three years from dormancy, under O.C.G.A. 9-12-6134.

New York deserves its own note, because its renewal is neither a rerecording nor a motion. An action on the money judgment may be begun in the year before ten years have passed since first docketing, and that action's judgment is docketed as a renewal judgment whose lien takes effect when the ten years expire, under CPLR 501435. There is a second New York device that reads like renewal and is not. On motion with notice, a court may keep the lien effective past ten years only for the time the creditor was stayed, or the time needed to finish a sheriff's sale under an execution delivered before the ten years ran, under CPLR 5203. It restores lost days. It does not hand back years nobody was stayed for.

Several of these routes may be used only once. Michigan, Kentucky, Oregon and Maine each allow one renewal, under MCL 600.2809, KRS 426.720, ORS 18.182 and 14 M.R.S. 4651-A36. Virginia allows one additional extension under Va. Code 8.01-25137. California allows one renewal for certain medical and personal-debt judgments under Cal. Code Civ. Proc. 683.11038, and a lien for a judgment in favor of the State of Texas or a state agency may be renewed once under Tex. Prop. Code 52.00639. Where the statutes name no renewal route for a state, this page names none in its place.

What lapses silently

Two things catch people after the lien is already theirs: a deadline that falls before the obvious expiry, and a renewal that keeps the judgment alive without keeping the lien. This section lists both. It says nothing about whether anyone tells you when a lien ends.

The deadline often comes early. Michigan and Kentucky want the renewal on file at least 120 days before the lien expires, under MCL 600.2809 and KRS 426.720. North Dakota renews a judgment first docketed before August 1, 2021 within the ninety days before ten years run, under N.D.C.C. 28-20-2140. New York's action must begin in the year before the tenth anniversary of first docketing, under CPLR 5014. A late Oregon certificate of extension simply has no effect, under ORS 18.182.

Worse is the renewal that does not reach the lien. In North Carolina an action on the judgment may be brought within ten years, but it does not continue the lien of the original judgment, under N.C. Gen. Stat. 1-4741. In Arkansas, what tolls or renews the judgment's limitation period does not revive or extend the lien, under Ark. Code 16-65-11742. In California a renewal does not extend the lien against a recorded transferee unless the application is served as Cal. Code Civ. Proc. 683.180 requires. Renewing the debt is not the same act as saving the security.

Each county is its own filing. Utah requires the renewing document in every county where the lien stands recorded, under Utah Code 78B-5-202. Oregon extends a lien in another county only by recording there first, under ORS 18.15243. Colorado wants the revived transcript in the same county as the original transcript, under C.R.S. 13-52-102. And Ohio's lien in a second county ceases unless one of the listed acts occurs there, under Ohio Rev. Code 2329.07. A renewal filed in one courthouse does nothing for a lien in the county next door.

A few traps are narrower and worth knowing cold. A Michigan debtor's state or federal insolvency filing does not toll or suspend the lien's clock, under MCL 600.2809. And Florida's lien on personal property is a creature apart from its real property lien: it lapses five years after the certificate is filed, under Fla. Stat. 55.20444. One second lien may be filed within six months either side of the lapse, but it is a new lien dated from its own filing. Not a continuation. No third may follow. When the second one lapses, the door is closed.

Time the creditor is stayed does not always count against these clocks, which is the one mercy in the picture. North Carolina, Nevada, Mississippi, Indiana, Kansas and the District of Columbia each exclude stayed time, under N.C. Gen. Stat. 1-23445, NRS 17.15046, Miss. Code 15-1-4747, IC 34-55-9-2, K.S.A. 60-240348 and D.C. Code 15-101. North Carolina's exclusion is not absolute: it does not run against a purchaser, creditor or mortgagee in good faith. Which act starts a priority clock, as against which one ends a lien, is the subject of priority by recording date. Nobody writing this is a lawyer and none of it is advice. Whether to renew a lien, and by which filing, is a question for counsel with your file open. What a page can do is narrower: name the clock, name the filing, and leave the arithmetic to the person holding the judgment.

Sources

Every section named above, with how current the text we read was. Read any of them yourself.

  1. CPLR 5203, Priorities and liens upon real property. Current through January 01, 2026. Read the section, opens in a new tab Back
  2. CPLR 5018, Docketing of judgment. Current through January 01, 2026. Read the section, opens in a new tab Back
  3. C.R.S. 13-52-102, Courts and Court Procedure § 13-52-102. Property subject to execution--lien--real estate. Read the section, opens in a new tab Back
  4. IC 34-55-9-2, Civil Law and Procedure § 34-55-9-2. Read the section, opens in a new tab Back
  5. IC 34-11-2-12, Civil Law and Procedure § 34-11-2-12. Read the section, opens in a new tab Back
  6. Iowa Code 624.23, Judicial Branch and Judicial Procedures [Chs. 595-686] § 624.23. Liens of judgments--real estate--homesteads--support judgments. Read the section, opens in a new tab Back
  7. Iowa Code 614.1, Judicial Branch and Judicial Procedures [Chs. 595-686] § 614.1. Period. Read the section, opens in a new tab Back
  8. Ala. Code 6-9-211, 6-9-211 Judgment Constitutes Lien on Property of Defendant. Every judgment, a certificate of which has been filed as pro. Read the section, opens in a new tab Back
  9. Ala. Code 6-9-190, 6-9-190 Revival Barred After 20 Years. A judgment cannot be revived after the lapse of 20 years from its entry. (Code 18. Read the section, opens in a new tab Back
  10. MCL 600.2809, Revised Judicature Act of 1961 § 600.2809. Read the section, opens in a new tab Back
  11. D.C. Code 15-101, Judiciary and Judicial Procedure § 15-101. Enforceable period of judgments;  expiration.. Read the section, opens in a new tab Back
  12. HRS 657-5, Courts and Judicial Proceedings § 657-5. Read the section, opens in a new tab Back
  13. W. Va. Code 38-3-6, Liens § 38-3-6. Lien of judgment on real estate. Read the section, opens in a new tab Back
  14. Ohio Rev. Code 2329.07, Courts Common Pleas § 2329.07. Read the section, opens in a new tab Back
  15. Neb. Rev. Stat. 25-1515, Courts; Civil Procedure § 25-1515. Judgment; when dormant. Read the section, opens in a new tab Back
  16. Wyo. Stat. 1-17-307, Code of Civil Procedure § 1-17-307. When judgment becomes dormant. Read the section, opens in a new tab Back
  17. O.C.G.A. 9-12-60, Civil Practice § 9-12-60. Read the section, opens in a new tab Back
  18. 12 O.S. 735, A judgment shall become unenforceable and of no effect if, within five (5) years after the date of filing of any judgmen. Read the section, opens in a new tab Back
  19. NMSA 39-1-6, Judgments, Costs, Appeals § 39-1-6. Money judgment; docketing; transcript of judgment; lien on real estate; supersedeas. Read the section, opens in a new tab Back
  20. Fla. Stat. 55.10, Judgments, orders, and decrees; lien of all, generally; extension of liens; transfer of liens to other security. 2026 Florida Statutes. Read the section, opens in a new tab Back
  21. Fla. Stat. 55.081, Statute of limitations, lien of judgment. 2026 Florida Statutes. Read the section, opens in a new tab Back
  22. KRS 426.720, Provisional Remedies, Enforcement of Judgments, and Exemptions § 426.720.Final judgment to act as lien on realty; judgment creditor's notice requirements; methods of service; expiration of judgment lien. Read the section, opens in a new tab Back
  23. Utah Code 78B-5-202, Judicial Code § 78B-5-202. Duration of judgment--Judgment as a lien upon real property--Abstract of judgment--Small claims judgment not a lien--Appeal of judgment--Child support orders. Read the section, opens in a new tab Back
  24. Cal. Code Civ. Proc. 683.120, California Code, Code of Civil Procedure - CCP § 683.120. Read the section, opens in a new tab Back
  25. Cal. Code Civ. Proc. 683.180, California Code, Code of Civil Procedure - CCP § 683.180. Read the section, opens in a new tab Back
  26. Md. Rule 2-625, Md. Rule 2-625. Read the section, opens in a new tab Back
  27. Miss. Code 15-1-43, Limitations of Actions and Prevention of Frauds § 15-1-43. Read the section, opens in a new tab Back
  28. ORS 18.182, Oregon Revised Statutes Procedure in Civil Proceedings § 18.182. Read the section, opens in a new tab Back
  29. Idaho Code 10-1111, Issues, Trial and Judgment in Civil Actions § 10-1111. Orders renewing judgment--Lien. Read the section, opens in a new tab Back
  30. D.C. Code 15-103, Judiciary and Judicial Procedure § 15-103. Effect of revival.. Read the section, opens in a new tab Back
  31. 735 ILCS 5/12-101, Civil Procedure § 5/12-101. Lien of judgment. Read the section, opens in a new tab Back
  32. K.S.A. 60-2404, Procedure, Civil § 60-2404. Revivor of dormant judgment. Read the section, opens in a new tab Back
  33. Pa.R.C.P. 3025, Pa.R.C.P. 3025. Read the section, opens in a new tab Back
  34. O.C.G.A. 9-12-61, Civil Practice § 9-12-61. Read the section, opens in a new tab Back
  35. CPLR 5014, Action upon judgment. Current through January 01, 2026. Read the section, opens in a new tab Back
  36. 14 M.R.S. 4651-A, Court Procedure--Civil § 4651-A. Execution liens. Read the section, opens in a new tab Back
  37. Va. Code 8.01-251, Civil Remedies and Procedure § 8.01-251. Limitations on enforcement of judgments. Read the section, opens in a new tab Back
  38. Cal. Code Civ. Proc. 683.110, California Code, Code of Civil Procedure - CCP § 683.110. Read the section, opens in a new tab Back
  39. Tex. Prop. Code 52.006, Duration of Lien. Read the section, opens in a new tab Back
  40. N.D.C.C. 28-20-21, Judicial Procedure, Civil § 28-20-21. Renewal of judgments by affidavit. Read the section, opens in a new tab Back
  41. N.C. Gen. Stat. 1-47, Civil Procedure § 1-47. Ten years. Read the section, opens in a new tab Back
  42. Ark. Code 16-65-117, Practice, Procedure, and Courts § 16-65-117. Judgment liens on real estate. Read the section, opens in a new tab Back
  43. ORS 18.152, Oregon Revised Statutes Procedure in Civil Proceedings § 18.152. Read the section, opens in a new tab Back
  44. Fla. Stat. 55.204, Duration and continuation of judgment lien; destruction of records. 2026 Florida Statutes. Read the section, opens in a new tab Back
  45. N.C. Gen. Stat. 1-234, Civil Procedure § 1-234. Where and how docketed;  lien. Read the section, opens in a new tab Back
  46. NRS 17.150, Civil Practice § 17.150. Docketing of judgments of state and federal courts; recording of transcripts, abstracts and copies of judgments; liens on real property; duration of liens; affidavit required of judgment creditor who records judgment or decree. Read the section, opens in a new tab Back
  47. Miss. Code 15-1-47, Limitations of Actions and Prevention of Frauds § 15-1-47. Read the section, opens in a new tab Back
  48. K.S.A. 60-2403, Procedure, Civil § 60-2403. Judgment, when dormant; release of record; child support judgments after July 1, 2007, never dormant; court costs, fees, fines and restitution judgments after July 1, 2015, never dormant. Read the section, opens in a new tab Back